20 May 2025 – Update: Progress on Concentrator Plant

WESIZWE PLATINUM LIMITED

(Incorporated in the Republic of South Africa)

(Registration number: 2003/020161/06)

Share code: WEZ

ISIN: ZAE000075859

(“Wesizwe” or the “Company”)

UPDATE: PROGRESS ON CONCENTRATOR PLANT

Shareholders are referred to the announcement released on SENS on 2 June 2023 advising

on the delays to the commissioning of the processing plant at the Bakubung Platinum Mine

project (“Project”) in Rustenburg as a result of defects identified in the initial test runs of the

plant.

In 2024 Wesizwe enlisted the services of experts to develop a comprehensive plant

rectification plan. An experienced contractor, Sinosteel, was brought on board to assist with

the rectification of the identified defects that included, but were not limited to, lube system

failure, excessive spillage on pulleys and trolleys and challenges with the hydraulic pump.

Since the initial announcement regarding the plant rectification, best efforts have been

invested to ensure Project success and to safeguard that the operation is able to commission

a fully operational processing plant that has capacity to meet the operation’s future

production targets.

After months of working tirelessly to ensure the success of the plant rectification we are

happy to announce that the Company’s plant rectification remains on track and has

commenced with the process of hot commissioning.

Further details will be communicated as soon as new information and progress is available.

Johannesburg

20 May 2025

Sponsor

PSG Capital