Bakubung Project Highlights
Key Milestones 2015
- The main shaft development has a new forecast completion date for the 920 m shaft in November 2015, which is 55 days ahead of schedule
- Similarly, the ventilation shaft is expected to reach its final depth of 880 m in September 2015, 144 days ahead of schedule
- Commissioning bulk water supply to the mine and 13 mega litres fresh feed per day for the community
- Commencement of waste development on multi-level through the ventilation shaft
- Implementation of the mine operational readiness plan
- Commencement of the process plant enquiry for the EPCM and front-end engineering (FEE)
Key Milestones 2016
- Commencement of the main shaft commission
- Continuation of waste development through the ventilation shaft
- Order long lead items for the process plant
- Progress mine operational readiness
- Commission phase 2 power supply of 60MW to the mine
- Achieved zero fatalities and LTIFR of 0.50
- Shaft equipping:
- Bunton sets 141
- All pipes 9 916 m
- All cabling deferred to 2017
- Station steelwork 53 t
- Loading box 114 t
- Holing achieved on 81 L
- Service shaft flat development 799 m
- Flat development
- Service shaft flat development 799 m
- Construction of surface package
- Scope deferred as part of board approved deferral initiative
- Banksman’s cabin: Scope was initiated in 2016, completion was planned for early 2017
- Control room was initiated in 2016; completion was planned for early 2017. Design change resulted in medical facility being moved to 2017
- Scope was initiated in 2016, completion was planned for early 2017
- Surface effluent civils: Scope completed
- Phases 1c and 1a and the 50 million reservoir completion:
- All phases completed on time
- Ngwedi-Bakubung OH line commission Phase 2 and 3. Bakubung Substation commissioned: Phase 2 commissioned successfully in December 2016
Key Milestones 2017
- Conclusion of shaft sinking
- Process plant construction commences
- Main shaft commissioned
- Production build-up commences
Key Milestones 2021
- Full production reached
- Concentrator modules 2 and 3 commissioned